12. 9. 2006

Information on NPP Temelín 179 / 2006

Unit 1 is in operation on planned power level. At Unit 2, the planned outage is continued that is connected with the yearly replacement of ¼ of the reactor fuel. All auxiliary systems are working in accordance with the operation needs of individual units.

September 12, 2006

Information on parameters at Unit 1 today on September 12, 2006 at 07:00 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 978 MWe
· Electricity production since the beginning of the year: 4 034 183 MWh

Information on parameters at Unit 2 today on September 12, 2006 at 07:00 o‘clock:
· Unit is in Mode 6
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 4 609 632 MWh

Václav Brom Spokesman of the Temelín NPP