The cold pressure test of the primary circuit of the Unit 1 was successfully completed yesterday at a pressure of 3,3 MPa. Its goal was to verify the tightness of the nuclear part of the power plant after the performed fuel substitution and back assembly of the reactor. Similar pressure test was successfully carried out also on the secondary part of the power station at a pressure of 1,8 MPa.
The test of operation of one of the two diesel generators common to both blocks was started yesterday in the evening after the planned revision. A defect on its motor emerged in the course of the test. The cause of the defect is investigated at present.
The works related to repeated start of the block go on; hot pressure tests of the primary circuit at a pressure of 17,6 MPa and of the secondary circuit at a pressure of 8,8 MPa will be performed at the weekend. The time schedule of outage supposes that the first block will re-initiate its operation at the end of September.
Information on parameters at Unit 1 today on September 14, 2007 at 10:15 o‘clock:
- Unit is in Mode 6
- Reactor power is 0 %
- Turbine generator output - 0 MWe
- Electricity production since the beginning of the year: 2 964 775 MWh
Information on parameters at Unit 2 today on September 14, 2007 at 10:15 o‘clock:
- Unit is in Mode 1 - power operation
- Reactor power is 100 %
- Turbine generator output - 1012 MWe
- Electricity production since the beginning of the year: 4 491 511 MWh