24. 9. 2007

Information on NPP Temelín 187 / 2007

Unit 2 is in operation at planned power level. At Unit 1, the reactor power will be increased to the 30 % RTP level, where the planned power tests will be carried out. All auxiliary systems of the power plant are working in accordance with the operation needs.

During the weekend, all planned physical tests have been performed at Unit 1. Among them, the test of the control organs (clusters) has been carried out. All the clusters have fallen to the end positions within the required times. The first spin of the modernized turbine to the operating speed (3000 rpm) is planned for today’s afternoon. The balancing of the machine will be monitored without its load by generator. After completion of all remaining planned power tests. Unit 1 will be anew prepared to start the electricity production and be synchronized to the power distribution grid.

Information on parameters at Unit 1 today on 24, September 2007 at 09:30 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 28 %
  • Turbine generator output - 0 MWe
  • Electricity production since the beginning of the year: 2 964 775 MWh

Information on parameters at Unit 2 today on 24, September 2007 at 09:30 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1006 MWe
  • Electricity production since the beginning of the year: 4 733 811 MWh