Yesterday morning, a short term power reduction of Unit 1 occurred. Its reason was the signal of the turbine driven feedwater pump protection that was brought about at the pump’s revision. The automatic systems have reduced the reactor power to 38 % RTP for a short time. The electricity delivery was not interrupted. The Unit reached the full power anew yesterday shortly after 4 o’clock p.m. After the output reduction, the complex 144 hours trial run of the modernized turbine set has been suspended. It has been restored yesterday at 6 o’clock p.m.
Information on parameters at Unit 1 today on October 10, 2007 at 9:30 o‘clock:
- Unit is in Mode 1 - power operation
- Reactor power is 100 %
- Turbine generator output - 1008 MWe
- Electricity production since the beginning of the year: 3 234 092 MWh
Information on parameters at Unit 2 today on October 10, 2007 at 9:30 o‘clock:
- Unit is in Mode 1 - power operation
- Reactor power is 100 %
- Turbine generator output - 1010 MW
- Electricity production since the beginning of the year: 5 093 635 MWh
Ing. Marek Sviták
Spokesman of the CEZ Group