12. 10. 2007

Information on NPP Temelín 200 / 2007

Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems of the power plant are in operation in accordance with the operational needs of the units.

Information on parameters at Unit 1 today on October 12, 2007 at 9:00 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1007 MWe
  • Electricity production since the beginning of the year: 3 282 627 MWh

Information on parameters at Unit 2 today on October 12, 2007 at 9:00 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1011 MW
  • Electricity production since the beginning of the year: 5 142 171 MWh

Václav Brom
Spokesman of the CEZ Group
Temelín NPP