18. 10. 2007

Information on NPP Temelín 204 / 2007

Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems of the power plant are in operation in accordance with the operational needs of the units.

Information on parameters at Unit 1 today on October 18, 2007 at 10:00 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1009 MWe
  • Electricity production since the beginning of the year: 3 428 238 MWh

Information on parameters at Unit 2 today on October 18, 2007 at 10:00 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1010 MW
  • Electricity production since the beginning of the year: 5 283 256 MWh

Ing. Marek Sviták
Spokesman of the CEZ Group
Temelín NPP