21. 10. 2008

Information on NPP Temelín 207 / 2008

Unit 2 is in operation at planned power level. At Unit 1, the outage is under way, that is connected with the revision of the third low pressure turbine generator. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on October 21, 2008 at 8:15 o‘clock:

  • Unit is in Mode 3 
  • Reactor power is 0 %
  • Turbine generator output - 0 MWe
  • Electricity production since the beginning of the year:  4 347 699 MWh

Information on parameters at Unit 2 today on October 21, 2008 at 8:15 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1010 MWe
  • Electricity production since the beginning of the year: 5 703 832 MWh

 

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín