21. 11. 2005
Information on NPP Temelín 225 / 2005
Unit 1 and Unit 2 are in operation at planned power level. All auxiliary systems are working in accordance with the operation modes of individual units.
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 980 MW
· Electricity production since the beginning of the year: 5 126 852 MWh Information on parameters at Unit 2 today on November 21, 2005 at 07:30 o’clock:
· Unit is in Mode 1 - power operation
· Reactor power is 76 %
· Turbine generator output - 725 MW
· Electricity production since the beginning of the year: 4 449 138 MWh Milan Nebesář
ČEZ, a.s., Spokesman