20. 11. 2006
Information on NPP Temelín 226/2006
Unit 1 is in operation at planned power. At Unit 2 the operators carried out a series of core physics tests at 30% of the reactor rated power and are preparing the synchronization to the national grid this evening.
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 973 MWe
· Electricity production since the beginning of the year: 5 529 686 MWh Information on parameters at Unit 2 today on November 20, 2006 at 07:30 o‘clock:
· Unit is in Mode 2
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 4 609 632 MWh Milan Nebesář
Spokesman of the Temelín NPP