Unit 1 is in operation at planned power. At Unit 2 the operators carried out a series of core physics tests at 30% of the reactor rated power and are preparing the synchronization to the national grid this evening.

November 20, 2006

All auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on November 20, 2006 at 07:30 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 973 MWe
· Electricity production since the beginning of the year: 5 529 686 MWh

Information on parameters at Unit 2 today on November 20, 2006 at 07:30 o‘clock:
· Unit is in Mode 2
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 4 609 632 MWh