8. 12. 2006
Information on NPP Temelín 240/2006
Unit 1 is in operation at planned power level. At Unit 2, an automatic intervention of the reactor limitation system occurred due to a false signal in the system of automata of the feedwater flowrate control to the steam generators in the secondary, non-nuclear part of the power plant today before noon.
All auxiliary systems are working in accordance with the operation needs of individual units. Information on parameters at Unit 1 today on December 7, 2006 at 13:30 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 980 MWe
· Electricity production since the beginning of the year: 5 929 350 MWh Information on parameters at Unit 2 today on December 7, 2006 at 13:30 o‘clock:
· Unit is in Mode 3
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 4 980 692 MWh Milan Nebesář
NPP Temelín Spokesman