INFORMATION ON NPP TEMELÍN 245 / 2024
Both Unit 1 and 2 is in the operation. The auxiliary systems are working in accordance with the operation needs of individual units.
Information on parameters at Unit 1:
- Unit is in the operation
- Turbine generator output – 1086 MWe
- Electricity production since the beginning of the year: 7 133 004 MWh
Information on parameters at Unit 2:
- Unit is in the operation
- Turbine generator output - 1095 MWe
- Electricity production since the beginning of the year: 7 191 078 MWh
News on the topic
- The Temelín Unit 2 produces electricity again. It will be in operation for fourteen months, two months longer than before.
- ČEZ will shut down Unit 2 this evening for inspections and replacement of fuel assemblies
- ČEZ evaluated bids for the construction of a new nuclear unit and named its preferred bidder, with results submitted to Ministry of Industry and Trade
- The first Temelín Unit produces electricity again. It has been shut down for two months to inspect and replace fuel assemblies