19. 12. 2006

Information on NPP Temelín 248/2006

Both Unit 1 and 2 are in operation at full rated power.

December 19, 2006

All auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on December 19, 2006 at 07:00 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 978 MWe
· Electricity production since the beginning of the year: 6 165 868 MWh

Information on parameters at Unit 2 today on December 19, 2006 at 07:00 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 98 %
· Turbine generator output – 998 MWe
· Electricity production since the beginning of the year: 5 237 500 MWh

Milan Nebesář
Spokesman of the Temelín NPP