6. 2. 2006

Information on NPP Temelín 25 / 2006

Unit 1 is in operation at planned power level. Unit 2 operates at half rated power and the planned physics tests are carried on at this power level.

February 3, 2006

Additional planned tests will take place at the power level of 90 % RTP. At the end of this week, the Unit will operate at full power. All auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on February 3, 2006 at 08:00 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 98 %
· Turbine generator output - 979 MW
· Electricity production since the beginning of the year: 752 150 MWh

Information on parameters at Unit 2 today on February 3, 2006 at 08:00 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 50 %
· Turbine generator output - 452 MW
· Electricity production since the beginning of the year: 63 833 MWh

Václav Brom NPP Temelín Spokesman