7. 2. 2006

Information on NPP Temelín 27/2006

Unit 1 and Unit 2 are in operation at planned power level. All auxiliary systems are working in accordance with the operation modes of individual units.

February 7, 2006

Unit 1 and Unit 2 are in operation at planned power level. All auxiliary systems are working in accordance with the operation modes of individual units.

Information on parameters at Unit 1 today on February 7, 2006 at 07:45 o’clock:
· Unit is in Mode 1 – power operation
· Reactor power is 98 %
· Turbine generator output - 978 MWe
· Electricity production since the beginning of the year: 846 146 MWh

Information on parameters at Unit 2 today on February 7, 2006 at 07:45 o’clock:
· Unit is in Mode 1 – power operation
· Reactor power is 97 %
· Turbine generator output – 980 MWe
· Electricity production since the beginning of the year: 149 736 MWh

Milan Nebesář
Spokesman of the Temelín NPP