9. 3. 2006

Information on NPP Temelín 49 / 2006

Unit 1 and Unit 2 are in operation at planned power level. All auxiliary systems are working in accordance with the operation modes of individual units.

March 9, 2006

Information on parameters at Unit 1 today on March 9, 2006 at 08:45 o’clock:
· Unit is in Mode 1 - power operation
· Reactor power is 97 %
· Turbine generator output - 982 MWe
· Electricity production since the beginning of the year: 1 505 415 MWh

Information on parameters at Unit 2 today on March 9, 2006 at 08:45 o’clock:
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 982 MWe
· Electricity production since the beginning of the year: 857 624 MWh

Václav Brom
Spokesman of the Temelín NPP