15. 3. 2006
Information on NPP Temelín 53/2006
Both Unit 1 and 2 are in operation at full rated power. All auxiliary systems are working in accordance with the operation needs of individual units.
· Unit is in Mode 1 - power operation
· Reactor power is 97 %
· Turbine generator output - 980 MW
· Electricity production since the beginning of the year: 1 646 560 MWh
Information on parameters at Unit 2 today on March 15, 2006 at 07:15 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 981 MW
· Electricity production since the beginning of the year: 999 231 MWh Milan Nebesář
Spokesman of the Temelín NPP