3. 4. 2007
Information on NPP Temelín 67 / 2007
Unit 2 is in operation at planned power level. At Unit 1, a planned outage is under way, that is connected with the annual refueling of ¼ of the reactor fuel. All auxiliary systems are working in accordance with the operation needs of individual units.
· Unit is in Mode 5
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 579 239 MWh Information on parameters at Unit 2 today on April 3, 2007 at 10:00 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 99 %
· Turbine generator output - 1010 MW
· Electricity production since the beginning of the year: 2 201 263 MWh Václav Brom
Spokesman of the CEZ Group Temelín NPP