INFORMATION ON NPP TEMELÍN 68 / 2023
The Unit 1 is in the operation in so-called power effect operation. During it, the operators will gradually reduce the power of the reactor by almost one percent a day. The operation on the power effect will finished on Friday April 7, by a planned shutdown for refueling. The Unit 2 is in the operation. The auxiliary systems are working in accordance with the operation needs of individual units.
Information on parameters at Unit 1:
- Unit is in the operation
- Turbine generator output – 1094 MWe
- Electricity production since the beginning of the year: 2 484 184 MWh
Information on parameters at Unit 2:
- Unit is in the operation
- Turbine generator output – 1104 MWe
- Electricity production since the beginning of the year: 2 483 273 MWh