4/6/2023
INFORMATION ON NPP TEMELÍN 69 / 2023
The Unit 1 is in the operation in so-called power effect operation. During it, the operators will gradually reduce the power of the reactor by almost one percent a day. The operation on the power effect will finished on Friday April 7, by a planned shutdown for refueling. The Unit 2 is in the operation. The auxiliary systems are working in accordance with the operation needs of individual units.
Information on parameters at Unit 1:
- Unit is in the operation
- Turbine generator output – 1081 MWe
- Electricity production since the beginning of the year: 2 510 430 MWh
Information on parameters at Unit 2:
- Unit is in the operation
- Turbine generator output – 1103 MWe
- Electricity production since the beginning of the year: 2 509 787 MWh
News on the topic
Temelín started to reduce its output in a planned manner and will initiate a two-month shutdown for refuelling on Friday night.
The Americans are going to supply nuclear fuel also to Dukovany, not only to Temelín
After preliminary assessment ČEZ has identified two preferred construction sites for small modular reactors, in addition to the Temelín pilot location, in Dětmarovice and Tušimice
Czech nuclear power plants announce record production