Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems of the power plant are working in accordance with the operation needs.

Information on parameters at Unit 1 today on April 16 2008 at 9:15 o‘clock:

  • Unit is in Mode 1 – power operation
  • Reactor power is 100 %
  • Turbine generator output - 1016 MWe
  • Electricity production since the beginning of the year: 1 927 8300 MWh

Information on parameters at Unit 2 today on April 16, 2008 at 9:15 o‘clock:

  • Unit is in Mode 1 - power operation 
  • Reactor power is 100 %
  • Turbine generator output - 992 MWe
  • Electricity production since the beginning of the year: 2 477 106 MWh

  