19. 4. 2007

Information on NPP Temelín 79/2007

Unit 2 is in operation at planned power. At Unit 1, works are under way on the drying of the collecting device of the generator exciter.

April 19, 2007

The technicians presume that the works will be shortened by 2 days and the Unit will be synchronized to the grid on Saturday. All auxiliary systems of the power plant are in operation in accordance with the operational needs of the units.

Information on parameters at Unit 1 today on April 19, 2007 at 7:00 o‘clock:
· Unit is in Mode 3
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 579 239 MWh

Information on parameters at Unit 2 today on April 19, 2007 at 7:00 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 100 %
· Turbine generator output - 1010 MW
· Electricity production since the beginning of the year: 2 590 045 MWh

Ing. Milan Nebesář
Spokesman of the CEZ Group
Temelín NPP