20. 4. 2007
Information on NPP Temelín 80 / 2007
Unit 2 is in operation at planned power level. At Unit 1, the operators brought the reactor into operation at 5:46 a.m. After the reactor power increase, the Unit will be synchronized to the grid tonight. All auxiliary systems are working in accordance with the operation needs of individual units.
· Unit is in Mode 2
· Reactor power is 1 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 579 239 MWh Information on parameters at Unit 2 today on April 20, 2007 at 09:00 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 100 %
· Turbine generator output - 1009 MW
· Electricity production since the beginning of the year: 2 614 339 MWh Václav Brom
Spokesman of the CEZ Group Temelín NPP