5. 5. 2008

Information on NPP Temelín 87 / 2008

Unit 1 is in operation at full rated power. Unit 2 is operated in the mode of power effect of reactivity. The auxiliary systems of the power plant are working in accordance with the operation needs.

Information on parameters at Unit 1 today on May 5, 2008 at 8:45 o‘clock:

  • Unit is in Mode 1 – power operation
  • Reactor power is 100 %
  • Turbine generator output - 1017 MWe
  • Electricity production since the beginning of the year: 2 391 122 MWh

Information on parameters at Unit 2 today on May 5, 2008 at 8:45 o‘clock:

  • Unit is in Mode 1 - power operation 
  • Reactor power is 88 %
  • Turbine generator output - 862 MWe
  • Electricity production since the beginning of the year: 2 908 792 MWh

 

Marek Sviták
Spokesman of the ČEZ GROUP
Temelín NPP