Unit 1 is in operation at planned power level. At Unit 2, the planned output is under way connected with the replacement of ¼ of the reactor fuel. All auxiliary systems are working in accordance with the operation needs of individual units.
· Unit is in Mode 1 - power operation
· Reactor power is 97 %
· Turbine generator output - 981 MWe
· Electricity production since the beginning of the year: 1 202 651 MWh Information on parameters at Unit 2 today on May 21, 2007 at 08:45 o‘clock:
· Unit is in Mode 6
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 2 975 006 MWh Marek Sviták