On Friday night, the Unit 1 of Temelín NPP will be as planned shut down for refueling
The technicians at the Temelín Nuclear Power Plant plan to perform over 16 thousand activities during the Unit 1 outage. The outage starts on Friday evening and ČEZ company plans it for a period of fewer than three months. During the outage, one third of the fuel will be replaced. The technicians will check the turbine and security systems or will modernize the pressurizer that is a device controlling pressure in the reactor. For the second time only, all outage works will be managed from a dedicated control center.