Nuclear Power Plant news pg. 2414

JE Temelin traffic

Information on NPP Temelín 145 / 2007

Both Unit 1 and 2 are in operation at full rated power. All auxiliary systems of the power plant are in operation in accordance with the operational needs of the units.

26. 7. 2007

JE Dukovany traffic

Information on Dukovany NPP, July 26th 2007

Units 1,2,3,4 are operated at full rated power. All auxiliary systems are working in accordance with operational needs of units. Electricity production since the beginning of operation: 273 872 455 MWh.

26. 7. 2007

JE Dukovany traffic

Information on Dukovany NPP, July 25th 2007

Units 1,2,3,4 are operated at full rated power. All auxiliary systems are working in accordance with operational needs of units. Electricity production since the beginning of operation: 273 829 322 MWh.

25. 7. 2007

JE Temelin traffic

Information on NPP Temelín 144 / 2007

Both Unit 1 and 2 are in operation at full rated power. All auxiliary systems of the power plant are in operation in accordance with the operational needs of the units.

25. 7. 2007