Information on NPP Temelín 26/2006
Unit 1 and Unit 2 are in operation at planned power level. All auxiliary systems are working in accordance with the operation modes of individual units.
6. 2. 2006
Information on NPP Temelín 25 / 2006
Unit 1 is in operation at planned power level. Unit 2 operates at half rated power and the planned physics tests are carried on at this power level.
6. 2. 2006
Information on NPP Temelín 24 / 2006
Unit 1 is in operation at planned power level. Today at 0:45 o?clock, Unit 2 has been synchronized with the power distribution grid and the electricity production has been restored.
2. 2. 2006
Information on NPP Temelín 23 / 2006