Nuclear Power Plant news pg. 1100

JE Temelin traffic

Information on NPP Temelín 190 / 2007

Unit 1 of the power plant Temelín was this morning at 03:10 re-connected to the power distribution grid. Unit 2 is in operation at planned power level. All auxiliary systems of the power plant are working in accordance with the operation needs.

27. 9. 2007

JE Temelin traffic

Information on NPP Temelín 189 / 2007

Unit 2 is in operation at planned power level. At Unit 1, the last power tests at the reactor power of 30% RTP will be completed today. All auxiliary systems of the power plant are working in accordance with the operation needs.

26. 9. 2007

JE Temelin traffic

Information on NPP Temelín 188 / 2007

Unit 2 is in operation at planned power level. At Unit 1, 3 "balancing runs" of the modernized turbine have been made at operating speed.

25. 9. 2007

JE Temelin traffic

Information on NPP Temelín 187 / 2007

Unit 2 is in operation at planned power level. At Unit 1, the reactor power will be increased to the 30 % RTP level, where the planned power tests will be carried out. All auxiliary systems of the power plant are working in accordance with the operation needs.

24. 9. 2007