Nuclear Power Plant news pg. 1100
Information on NPP Temelín 190 / 2007
Unit 1 of the power plant Temelín was this morning at 03:10 re-connected to the power distribution grid. Unit 2 is in operation at planned power level. All auxiliary systems of the power plant are working in accordance with the operation needs.
27. 9. 2007
Information on NPP Temelín 189 / 2007
Unit 2 is in operation at planned power level. At Unit 1, the last power tests at the reactor power of 30% RTP will be completed today. All auxiliary systems of the power plant are working in accordance with the operation needs.
26. 9. 2007
Information on NPP Temelín 188 / 2007
Unit 2 is in operation at planned power level. At Unit 1, 3 "balancing runs" of the modernized turbine have been made at operating speed.
25. 9. 2007
Information on NPP Temelín 187 / 2007
Unit 2 is in operation at planned power level. At Unit 1, the reactor power will be increased to the 30 % RTP level, where the planned power tests will be carried out. All auxiliary systems of the power plant are working in accordance with the operation needs.